Northern Bruce Peninsula council passed the motion to proceed with the replacement of twin culverts on Shaw Road.
Staff have already ordered the culverts as it is expected to take six to eight weeks for the materials to arrive. Staff have also asked the municipal drainage engineers to submit the necessary permit application to Fisheries and Oceans Canada to obtain authorization for work in or near the watercourse.
The deficiencies were found during the municipality’s 2026 Ontario Structure Inspection Manual review. B.M. Ross identified significant deficiencies in the twin culverts on Shaw Road, about 550 metres south of Little Pike Bay Road. The inspection found that both culverts have deteriorated to the point that they have separated from the rest of the structure.
Once the final scope of work is established and all required approvals are received, staff will evaluate the best construction method and hire a qualified local contractor to complete the work.
The final project cost is still being determined and will include material supply, installation, traffic control, restoration and any associated engineering or environmental compliance requirements.
“It’s likely not going to get done in the 2026 year,” says Public Works Manager Troy Cameron. “But at least now we are prepared as soon as we have everything ready to go.”